Civic Offices, Newcastle-under-Lyme

Location: Newcastle-under-Lyme Client: Newcastle-under-Lyme Borough Council Principal Contractor: Willmott Dixon Construction Ltd Value: £1,400,000 Timescale: July 2021 to June 2022 Scope: The asbestos removal, soft-strip, demolition and site clearance of the former civic offices. Project Background The project consisted of the demolition of the former 4-storey Civic Centre offices in the centre of Newcastle-under-Lyme.  The [...]

Premier House, Chester

Location: Premier House, Chester Client: Muse Developments Value: £450,000 Timescale: March 2018 to June 2018 Scope:The asbestos removal, soft-strip, demolition and site clearance of a 7-storey office building in Chester. Project Background The seven storey building was a 1970’s concrete framed, brick clad office block.  The block was situated in the commercial district in the [...]

Lincoln House, Manchester

Location: Deansgate, Manchester Client: Marcus Worthington & Co Ltd Principal Contractor: Forshaw Demolition Ltd Value: £1,000,000 Timescale: January 2017 to June 2017 Scope: The asbestos removal, soft-strip, demolition and site clearance of a former 11-storey office block in the centre of Manchester. Project Background The project consisted of two adjacent former office blocks (123 Deansgate and [...]

Queen’s Park Tower Blocks, Blackpool

Location: Blackpool Client: Lovell Partnerships Ltd Client’s Project Manager: Peter Lewis Value: £1,400,000 Timescale: February 2016 to October 2016 Scope: The soft-strip, demolition and site clearance of three residential tower blocks using controlled explosives. Demolition Background The three tower blocks consisted of two blocks of 17 storeys and one block of 23 storeys were situated [...]

Washington House, Salford

Location: New Bailey Street, Salford Client: English Cities Fund Client's Project Manager: English Cities Fund Value: £350,000 Timescale: March 2015 to July 2015 Scope: The asbestos removal, soft-strip, demolition and site clearance of a 7-storey office building. Site between railway station and River Irwell with busy streets on other sides. Background Information The seven storey building [...]

Salford Tower Blocks

Location: Salford Client: Urban Vision Partnership Ltd Value: £2,000,000 Timescale: September 2013 to May 2015 Scope: The soft-strip, deconstruction, demolition and site clearance of three 17-storey residential tower blocks. Project Background The three, seventeen storey tower blocks were of a Fran concrete panel construction with additional strengthening at the gables. One of the tower blocks [...]

West Gorton Regeneration, Manchester

Location: West Gorton, Manchester Client: Manchester City Council Principal Contractor: Balfour Beatty Construction Value: £2,671,000 Timescale: March 2013 to May 2014 Scope: The soft-strip, demolition and site remediation of several blocks of low rise properties and two 15-storey residential tower blocks Project Background The project involved two phases of work. The initial phase was to [...]

Chester House, Manchester

Location: Old Trafford, Manchester Client: Greater Manchester Police Main Contractor: Balfour Beatty Construction Client's Project Manager: White Young Green Value: £750,000 Timescale: January 2013 to June 2013 Scope: The soft-strip and demolition of an 11-storey office block - former headquarters of the Greater Manchester Police. Background Information This contract involved the demolition of the former headquarters of [...]

Concourse House, Liverpool

Location: Lime Street, Liverpool Client: Liverpool Vision for Liverpool Council Client's Project Manager: Martin Stockley Associates Value: £1,600,000 Timescale: July 2008 to March 2009 Scope: The soft-strip, deconstruction, demolition and site clearance of a 14-storey office building and adjacent shops and basements.  Site directly outside main city centre railway station with busy streets on other [...]

Cooper House, Manchester

Location: Manchester City Centre Client: Wilson Bowden Developers CDM Coordinator: Wilson Bowden Developers Engineering Consultant: Healey Brown Partnership Value: £750,000 Timescale: June 2006 to January 2007 Scope: The soft-strip, deconstruction, demolition and site clearance of a seven-storey office building with basement car park. Site adjacent to Lloyds TSB business centre with office buildings on all other [...]